Skip to main content

Building procurement method: Management

Management

Management procurement is a method where construction work is completed using a series of separate works or trade contracts which the main contractor is responsible for managing. The contractor does not actually do the physical work, but is paid a sum for managing the project through the various works packages.

The employer starts by appointing consultants and a contract administrator to prepare drawings, a project specification and cost plan. The employer has control over design throughout the project through their professional team. The contractor is appointed by negotiaiton or tender, and interview. The works packages are usually let by competitive tender.

It is beneficial for the proposed contractor to be involved as early as possible as they will provide expertise in terms of buildability and programming of the works packages.

Other features of management procurement

  • Design can proceed in parallel with construction, and much of the design might be of a specialist nature related to a specific package of work. Early starts on site are often possible and overall project time can be reduced as a result.
  • There is no certainty over cost at the outset and work proceeds on the basis of the cost plan. The final cost of the project will not be known until the final works package is let, however costs can be monitored and controlled by the employer's professional team.
  • Design changes are possible during the construction phase, provided that the changes do not affect work on packages already let, which can result in aborted work.
  • Completion within the contract period is an obligation of the contractor, and extensions of time cannot be granted without permission from the contract administrator.
  • Risk is largely with the employer, in respect of costs and time. A degree of trust and in-house expertise is required for management procurement projects. However this is a low risk option for the employer in terms of design and quality because of the control they have over the professional team.

Management Contracting vs. Construction Management

Management procurement generally works on the basis of two different methods:

Management Contracts

With management contracts, the employer appoints a professional team and a management contractor who is responsible for managing the works. The management contractor does not directly undertake any of the construction, this is spilt into packages and carried out by works contractors. The management contractor appoints the works contractors, and they are directly and contractually accountable to the management contractor. A pre-construction phase will allow a programme of works packages to be developed from the drawings, specification and cost plan, which are then let out by competitive tender.

Although contractually responsible for the works contractors, the management contractor is not liable for any default by a works contractor, provided they have complied fully with the terms of the management contract.

A variation on this method is 'design and manage' where the management contractor is responsible for the design team as well as the works contractors.

Construction Management

With construction management contracts, the employer will appoint a professional team with either an in-house manager, or enters an agreement with a construction manager to oversee the work. The construction manager does not directly undertake any of the construction work, this is split into packages and carried out by trade contractors. The employer appoints the trade contractors and is directly responsible for them. The construction manager manages the works, but the employer has a major role in directing the project.

Types of JCT Management Contracts

Credit to JCT

Comments

Popular posts from this blog

BIM (Building Information Modeling) မိတ်ဆက်

အခုအချိန်တွင် BIM ဆိုတဲ့ စကားလုံးကို ဆောက်လုပ်ရေးလောကမှာ အတော်များများ ပြောသံဆိုသံတွေ ကြားလာကြတယ်။ ဒါကြောင့် BIM ဘာကြီးမှန်း သိဖို့နဲ့ ဘယ်သူတွေက ဘယ်ကိစ္စတွေမှာ သုံးနေတယ် သုံးကြတယ် ဆိုတာကို အတိအကျသိဖို့ လိုပါလိမ့်မယ်။ တစ်ချို့က BIM သည် software တစ်မျိုးလို့ပြောတယ်။ တစ်ချို့က BIM သည် အဆောက်အဦးတွေရဲ့ 3D model လို့ဆိုကြပြန်တယ်။ တစ်ခြားလူတွေက BIM ဆိုတာ အဆောက်အဦးနဲ့ ပတ်သက်တဲ့ အချက်အလက်တွေ အကုန်လုံးကို သေသေခြာစုဆောင်း ပေးနိုင်တဲ့ လုပ်ငန်းစဉ် တစ်ခုလို့ ရှုင်းပြကြပြန်တယ်။ တစ်ကယ်တော့ BIM ဆိုတာ ခုနကပြောခဲ့တဲ့ အကြောင်းအရာတွေ အကုန်လုံးထက် အများကြီးကိုပိုသ ပြီးလုပ်ဆောင်ပေးနိုင် ပါသေးတယ်။  သာမန်လူတစ်​ေယာက်၊ ဆောက်လုပ်ရေးလောက ပြင်ပကလူတစ်ယောက် နားလည်အောင် ရှင်းပြရရင် BIM ဆိုတာဖြစ်လာဖို့ အတွက် digital 3D model ကို စပြီးတည်ဆောက်ရတယ်။ အဲဒီ model က သာမန် 3D model ထက်ပိုပြီး အခက်အလက်တွေကို ထည့်သွင်း ဖေါ်ပြတယ်။ ဆိုကြပါစို့ လှပပြီး စိတ်ဝင်စား စရာကောင်းတဲ့ နံရံတွေရဲ့ ဆေးရောင်တွေ၊ texture တွေ ကိုတစ်ပါတည်း ထည့်သွင်းဖေါ်ပြလို့ရပါတယ်။ BIM model တစ်ခု ဖြစ်လာဖို့ဆိုရင် တစ်ကယ့်အဆောက်အဦးမှာ ပါတယ့် စိတ်အပိုင်းတွေ အက...

Amazing poster outside Raffles City

Once upon a time in Singapore, there is a enormous shopping center called Raffles City which held a colorful vinyl poster outside of its wall is located at the heart of the island state. As it is located in very important place, thousands and thousands of people passed trough in front of the building every week and observed the strange picture and murdered 'Splendid' soon after they gazed and found out the awe of it. တစ္ခ်ိန္တုန္းက စင္ကာပူဆိုတဲ့ ကြ်န္းႏိုင္ငံေလးရဲ့ ျမိဳ႔လယ္မွာ သိပ္ကိုၾကီးမားတဲ့ Raffles City လို႔ အမည္ရတဲ့ Shopping Center အၾကီးၾကီးတစ္ခုရွိသတဲ့။ အပတ္စဥ္ လူေထာင္ေပါင္းမ်ားစြာတို႔ဟာ အဲဒီဆိုင္ၾကီးရဲ့ အျပင္ဖက္ နံရံမွာ အေရာင္အေသြးစံုလင္လွတဲ့ Vinyl Poster ၾကီးတစ္ခုရွိကို ဆိုင္ေရွ႔က ဖ်တ္သြားေငးၾကည့္ေလ့ရွိျပီး ဒီ Poster ၾကီးရဲ့ ထူးဆန္း အံၾသဖြယ္ အလွတရားကို ေတြ႔ရွိျပီေနာက္ လူတို္င္းက "သိပ္ကို အံၾသစရာေကာင္းပါလား" ဆိုတဲ့ စကားကို ေရရြတ္ေလ့ရွိၾကသတဲ့။ This was what we saw the vinyl in our naked eyes. A boy and a mouse on his left cab be seen. အခု ပံုက သာမန္ မ်က...